Dune Walkover Replacement

Dune Walkover Replacement- Estimated Timeline

 

The following information is being distributed with regards to the replacement of Dune Walkovers that were severely damaged during Hurricane Matthew and Hurricane Irma.  The estimated timeline below reflects the schedule of work necessary for replacement of Dune Walkovers at the following specific locations; 13th Street South, 15th Street South, 17th Street South, North 20th Street and North 22nd Street.

Please remember the estimated timeline is dynamic and may be subject to change:

Permits for replacement of the aforementioned Dune Crossovers have provided to the Florida Department of Environmental Protection (FDEP) and are currently being reviewed.

South of SR100:  Pile driving operations for the three (3) replacement Dune Walkovers South of SR100, (13th, 15th and 17th Streets South) is scheduled to occur between April 12th and April 21st.  Above ground construction (deck, bracing, railings, steps, etc.) of the Dune Walkovers is scheduled for April 23rd through May 25th.

North of SR100:  Pile driving operations for the two (2) replacement Dune Walkovers North of SR100, (North 20th and North 22nd Streets) is scheduled to occur between April 23rd and April 30th.  Above ground construction (deck, bracing, railings, steps, etc.) of the Dune Walkovers is scheduled for May 29th through June 15th.

“As a City, the replacement of Dune Walkovers that were destroyed by Hurricanes Matthew and Irma has been a priority and a lot of hard work has been put in to make this a reality” said City Manager, Larry Newsom. Mr. Newsom concluded by stating “I’m proud of the work that’s been done so far and we’re looking forward to these five (5) Dune Walkovers being replaced and re-opened to the public in mid-June”.  If there’s any updated information with regards to the estimated timeline, a Public Service Announcement will be released.